男女羞羞视频在线观看,国产精品黄色免费,麻豆91在线视频,美女被羞羞免费软件下载,国产的一级片,亚洲熟色妇,天天操夜夜摸,一区二区三区在线电影
Global EditionASIA 中文雙語Fran?ais
China
Home / China / National affairs

Rising to a tunnel's challenge

By China Daily | China Daily | Updated: 2017-06-09 07:32
Share
Share - WeChat

Workers deal with gushing water during the construction of the Dazhushan Tunnel on the Dali-Ruili Railway project in May.Provided To China Daily

When work began on the Dazhushan Tunnel, the plan was to finish it in five years. That was in 2008 - and construction crews are still digging.

Unexpected difficulties mean the 14.5-kilometer tunnel, a critical juncture on the Dali-Ruili Railway in Yunnan province, is now scheduled for completion in 2021, Xinhua News Agency reported.

The tunnel runs through six faults in the Hengduan Mountains on the Qinghai-Tibet Plateau. It would have been beyond imagination to build on the earth fractures 20 years ago, said You Hongsheng, a spokesman for No 4 Company of China Railway First Group Co, which is digging the tunnel.

In August 2009, immediately after the first drilling began at one of the six fault lines, a 20-centimeter crack appeared in the operating face. The crack continued to widen as mudrock gushed out, filling a space 200 meters long and 6 meters high in about five hours.

"We failed to predict the fragility of the fault," said Jiang Dong, a construction manager at the site. "It is just like drilling into a piece of bean curd. The mudrock started to flow into the tunnel as we worked."

Jiang said the problem was later solved by building a wall to stop the mudrock flow and grouting the flow until it became solid. "Then we dug through the solid part to carry on with the project."

 

An estimated 140 million cubic meters of water have been pumped out of the tunnel over the past nine years of construction work.

In addition to the day-to-day operating challenges, the geologic complexity of the area where the tunnel is located has made working conditions extremely tough for workers.

In most parts of the construction site, it's quite humid, with the temperature in the hole at around 37 C. Workers had to alternate in two-hour shifts to continue through the day.

Some workers have left the project because of the rough working conditions and the extended construction time. Others, however, stayed put and were determined to hold their ground until the tunnel's completion.

Jiang said when he began working at the site his daughter was in second grade, and now she is in senior high school. He has been able to be home for just 20 days every year.

Wu Hao, 25, chose to stay with the project even though his father needed him in the family business.

"I need to prove myself in this project. How can I give up halfway?" Wu said.

When the Dali-Ruili Railway is complete, it will take a train just five minutes to run through the tunnel. Few passengers will know that it took 13 years to build.

 

Top
BACK TO THE TOP
English
Copyright 1994 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
 
主站蜘蛛池模板: 肇庆市| 太和县| 怀化市| 松潘县| 河源市| 长汀县| 丰宁| 伊川县| 甘谷县| 诸城市| 北碚区| 沾益县| 澎湖县| 乌拉特前旗| 田东县| 封开县| 延津县| 铁力市| 万源市| 陆丰市| 彰武县| 扬州市| 吉隆县| 湖口县| 车致| 临安市| 延长县| 秦皇岛市| 吐鲁番市| 义乌市| 临武县| 东安县| 渝北区| 稷山县| 偏关县| 五莲县| 神农架林区| 宜兰市| 玉门市| 宽甸| 德格县| 临邑县| 建平县| 柳河县| 察雅县| 咸宁市| 左云县| 沧源| 公主岭市| 吉木乃县| 清丰县| 弥勒县| 新河县| 德清县| 湄潭县| 特克斯县| 巴林左旗| 建平县| 灵川县| 遂溪县| 西林县| 偃师市| 平原县| 克什克腾旗| 舟山市| 乌兰县| 和平县| 乳山市| 林西县| 山阳县| 浦东新区| 呼图壁县| 周宁县| 盐山县| 弋阳县| 通化市| 潼关县| 额济纳旗| 阳东县| 纳雍县| 昔阳县| 赞皇县|