Land compensation to facilitate smooth construction of SGR phase 2A

By EDITH MUTETHYA | chinadaily.com.cn | Updated: 2018-06-29 23:25
Share
Share - WeChat
CRBC workers restore vegetation at the Nairobi National Park section of the Nairobi-Naivasha SGR. [Liu Hongjie/China Daily]

China Road and Bridge Corporation (CRBC) is set to continue with the construction of the phase 2A of the Standard Gauge Railway (SGR) following the start of fast-tracking of land acquisition and compensation process by relevant authorities.

The extension of the railway line had been delayed by increased land disputes by groups and families along the route.

To solve the issue as well as ensure that the contractor carries out activities smoothly, the Ministry of Lands, National Lands Commission and Kenya Railways have deployed land surveyors and valuers to various sites along the Nairobi – Naivasha SGR route to fast track the land acquisition and compensation process.

The professionals will be on ground for the next two weeks to facilitate awards and final payments to owners with official and proper documentation.

This follows a directive by President Uhuru Kenyatta to have the compensation process finalized by the end of July to pave way for completion of the project envisaged to be launched on May 31, 2019.

On June 23, president Kenyatta accompanied by key Cabinet Secretaries involved in the project, undertook an inspection of the on-going SGR Phase 2A construction to assess the progress and deliberate on the best course of action.

While the progress made is commendable, Kenyatta noted some key areas that needs immediate improvement.

Top on his list was the land acquisition issue which he stressed should be fast tracked and all project affected persons compensated within a month to enable the contractor, China Road and Bridge Corporation, go on with construction activities unhindered by unavailability of land.

Kenya Railways is responsible for determining and surveying the land required for the project, after which the Ministry of Lands provides a pricing index for the identified area for compulsory acquisition while NLC undertakes valuation of the identified land, gives awards and makes payment to project affected persons.

Most Viewed in 24 Hours
Top
BACK TO THE TOP
English
Copyright 1994 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
主站蜘蛛池模板: 泰宁县| 漾濞| 什邡市| 宜兰县| 滦平县| 米泉市| 合水县| 乐安县| 阳城县| 马山县| 观塘区| 双牌县| 长宁区| 铜山县| 桦川县| 铁岭市| 东乌| 同心县| 内乡县| 万山特区| 罗甸县| 庆云县| 林周县| 石家庄市| 普宁市| 二手房| 同江市| 汉川市| 平昌县| 迁西县| 布尔津县| 镇赉县| 伊春市| 顺义区| 乌鲁木齐市| 河池市| 资溪县| 额济纳旗| 太谷县| 定陶县| 邯郸县| 吴川市| 时尚| 阜城县| 嘉义县| 孝昌县| 洪江市| 绿春县| 东莞市| 边坝县| 乐清市| 丰宁| 泸定县| 灵璧县| 嘉定区| 新民市| 阆中市| 大兴区| 神农架林区| 临夏市| 东光县| 建宁县| 邵武市| 福州市| 桃源县| 徐水县| 银川市| 女性| 麦盖提县| 江油市| 锡林浩特市| 晋宁县| 呼伦贝尔市| 鹿泉市| 常宁市| 正宁县| 永寿县| 安康市| 泸西县| 进贤县| 凤阳县| 恭城|