Medical facilities reflect mainland engineering efficiency

By Su Zihan in Hong Kong | chinadaily.com.cn | Updated: 2021-10-28 12:36
Share
Share - WeChat
This photo shows a view of the Specimen Reception Counter at the North Lantau Hospital Hong Kong Infection Control Centre on Oct 27, 2021. [Photo by EDMOND TANG / CHINA DAILY]

Editor's notes: In a Tuesday lecture, Zhang Yi, CEO of China State Construction International Medical Industry Development Corp, shared with Hong Kong students the stories behind the construction of two Hong Kong medical facilities built with the nation's help to combat the COVID-19 pandemic.

Here are the profiles of the two projects and some impressive figures from Zhang's speech.

North Lantau Hospital Hong Kong Infection Control Centre

Started operation on Feb 26, 2020

Building area: 44,000 square meters

Floor space: 29,000 square meters

Facilities: 6 ward buildings, 1 medical center building, 1 energy center building, 1 liquid oxygen station, 1 dangerous-goods warehouse and some other ancillary facilities

Beds: 816 negative-pressure isolation beds

Service life: Permanent building

Community treatment facilities at AsiaWorld-Expo

China's first high-standard intelligent negative-pressure mobile cabin hospital

Started operation on Aug 1, 2020

Building area: 30,000 square meters

Facilities: 40 negative pressure isolation wards with a total of 160 beds

792 beds in general square cabins

32 communal facilities, including nurses stations

Provision of additional air-conditioning facilities

Beds: 952

Efficiency and safeguards of the two projects

-Finished 21 versions of designs in 7 days

-Shortened the construction period of the temporary hospital from 3 to 4 years to 4 months

-Cumulative number of workers on site exceeds 240,000, with over 4,000 workers worked on-site a day at the peak of the construction

-Over 200 subcontractors and 130 suppliers in Hong Kong served as a backup team

-Procured materials and equipment from nearly 20 countries or regions around the world. The transportation volume reached the loads of more than 40,000 trucks.

Top
BACK TO THE TOP
English
Copyright 1994 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
 
主站蜘蛛池模板: 郎溪县| 宁强县| 湘乡市| 青田县| 旬阳县| 东方市| 宁武县| 冕宁县| 湄潭县| 扶余县| 高雄市| 辉县市| 永德县| 绥德县| 乌拉特前旗| 汝城县| 德化县| 德安县| 梁河县| 若羌县| 田阳县| 筠连县| 呈贡县| 胶南市| 岑溪市| 永定县| 修文县| 阳朔县| 眉山市| 关岭| 垦利县| 井冈山市| 陇南市| 江永县| 天祝| 红原县| 方正县| 盈江县| 南投县| 秭归县| 台州市| 华阴市| 玉山县| 土默特左旗| 西盟| 屏山县| 永兴县| 南康市| 都兰县| 临沭县| 手游| 盈江县| 平定县| 曲阜市| 安龙县| 宣化县| 宜都市| 麻城市| 兴义市| 宜城市| 怀仁县| 高邮市| 永靖县| 昌图县| 阿图什市| 渭南市| 大洼县| 大埔区| 隆回县| 古交市| 临汾市| 漳浦县| 时尚| 乐陵市| 横山县| 三明市| 涿州市| 宜兰县| 内丘县| 崇信县| 徐闻县| 楚雄市|