Generating units pass full generation capacity test

(Xinhua)
Updated: 2006-10-30 08:56

Fourteen generating units of the Three Gorges Project, the world's largest hydropower plant, have passed a 72-hour full operating capacity test, an official in charge of the project said on Sunday.

Over a period of three days ending 9:00 a.m. Sunday, the 14 units generated 700,000 kw/hour of electricity without showing any signs of instability, said Li Yong'an, general manager of the China Three Gorges Project Corporation.

Li said generator performance can only be tested thoroughly by putting them through a 72-hour full capacity test.

This is the first time that China has independently operated such a big group of generating units. There are only 37 generating units with a capacity of 700,000 kw/hour in the entire world.

The water level in the Three Gorges Reservoir began to rise from the 135.5 meter mark on September 20 and reached the 156 meter mark on Friday.

According to the original design, a water level of 148 meters is required for full generation capacity.

The 14 generating units underwent a one-day full generation capacity test on October 18.
Since being commissioned in 2003, the units had been generating 550,000 kw/hour of electricity from the lower water level in the Three Gorges Reservoir, Li said, adding the successful test shows that generating units have coped well with the rising water level.

Currently, more than 1.2 million people, or over 85 percent of those covered by the
original plan, have been relocated to make way for the gigantic project and rest will be resettled before the water level in the reservoir reaches 175 meters in 2008, one year earlier than scheduled.

Launched in 1993 and being built at an estimated cost of 180 billion yuan (about 22.5 billion U.S. dollars), the Three Gorges Project on the middle reaches of the Yangtze River, China's longest, will eventually have 26 generators with a combined generating capacity of 18.2 million kw and be able to generate 84.7 billion kwh of electricity annually.

The other 12 generating units are still under construction.

As of Sunday, the Three Gorges Project had generated over 138 billion khw of electricity.

(For more biz stories, please visit Industry Updates)

 
 

主站蜘蛛池模板: 海口市| 青铜峡市| 南郑县| 梅河口市| 正蓝旗| 肥城市| 临沧市| 西昌市| 铁力市| 资溪县| 科尔| 武陟县| 葵青区| 高密市| 虞城县| 泌阳县| 林州市| 枞阳县| 安泽县| 满洲里市| 柏乡县| 论坛| 抚州市| 安阳市| 大方县| 武邑县| 甘孜县| 青铜峡市| 浙江省| 扎赉特旗| 调兵山市| 香格里拉县| 哈尔滨市| 忻州市| 宁蒗| 和平县| 恩施市| 绥阳县| 黎川县| 青铜峡市| 永宁县| 利川市| 滦平县| 焉耆| 工布江达县| 宁武县| 敖汉旗| 桦南县| 乐陵市| 石屏县| 焉耆| 汉源县| 莱州市| 额尔古纳市| 岱山县| 留坝县| 南丹县| 台中市| 保定市| 凤台县| 信宜市| 财经| 晋城| 巴里| 哈尔滨市| 闽侯县| 融水| 富平县| 高青县| 瑞丽市| 昌邑市| 同德县| 延安市| 新营市| 衡阳市| 东丽区| 高淳县| 建宁县| 林口县| 贡嘎县| 调兵山市| 吉木萨尔县|