Hurdles drag wind power sector

By Zheng Lifei (China Daily)
Updated: 2007-04-19 08:47
Large Medium Small

Hurdles drag wind power sectorChina's wind power industry is set to grow, but hurdles need to be cleared if it is to catch up with global players, say analysts.

Since the first wind farm was erected and connected to the grid in 1986 in East China'sShandongProvince, China has built 61 such facilities, according to figures from Chinese Renewable Energy Industries Association.

The figure may have reached 80 by the end of last year, with installed wind power capacity amounting to 2,300 megawatts, making China the world's seventh-largest producer, said Chen Yicong, a wind energy industry analyst at Southwest Securities.

But impressive growth still pales in comparison with the country's potential, experts said at a recent industry forum inShanghai.

China boasts a 1,000-gigawatt reserve of exploitable wind energy, of which 250 gigawatts are on land and 750 gigawatts offshore, according to Shi Pengfei from China Hydropower Consultants Ltd, aBeijing-based consultancy.

The installed wind power capacity only accounted for 0.38 percent of the country's total power generation capacity in 2005, according to Energy Research Institute, affiliated with the country's top economic policymaking agencyNational Development and Reform Commission.

Related readings:
Hurdles drag wind power sectorInstalled capacity of wind power expected to top 5m kw next year
Hurdles drag wind power sectorShanghai to build wind power plant
Hurdles drag wind power sectorWind power investors plan to quit Inner Mongolia market

It estimates that the proportion was still under 0.5 percent last year. In comparison, in Denmark, which has one of the world's most developed wind power industry, 20 percent of the installed power capacity comes from wind power. In India, the figure is 3 percent, according to Chen.

China is aiming to increase its wind power capacity to 30,000 megawatts by 2020, up from the previous goal of 20,000 megawatts, according to a blueprint issued in 2005 by the NDRC.

Many experts think the goal can be met much earlier if the major hurdles to wind power development are removed.

In addition to the natural limits associated with wind power generation such as the need for sparsely populated areas and the unstable nature of wind, which may affect the stability of the grid, there are other hindrances, said Chen.

"The costs of construction of wind farms in China are significantly higher than that of conventional power plants because of the exorbitant prices of imports," Chen said.

Wind power rates, therefore, are much higher than those of hydropower and coal- or gas-fired power, making investors less inclined to enter the market.

   Previous Page 1 2 Next Page  

分享按鈕
主站蜘蛛池模板: 禹州市| 明水县| 阿克苏市| 开原市| 玉龙| 交城县| 砚山县| 和田县| 盐池县| 田东县| 庄河市| 堆龙德庆县| 新宾| 洪雅县| 黄浦区| 福清市| 阜康市| 广德县| 湘阴县| 鞍山市| 达州市| 抚松县| 浮山县| 育儿| 新乡市| 定日县| 彰武县| 澎湖县| 清苑县| 清水县| 慈利县| 滕州市| 东丰县| 临颍县| 昭平县| 井冈山市| 邓州市| 苏尼特右旗| 缙云县| 信丰县| 工布江达县| 奉节县| 新昌县| 巴彦县| 云浮市| 天水市| 杭州市| 治县。| 忻城县| 紫金县| 阳江市| 贞丰县| 曲周县| 河池市| 香港 | 监利县| 宜良县| 康定县| 阜新| 昭觉县| 郎溪县| 平舆县| 甘孜县| 钟山县| 饶平县| 宜春市| 鄱阳县| 西宁市| 治多县| 天峨县| 江西省| 双桥区| 肥城市| 三明市| 军事| 康平县| 怀柔区| 崇仁县| 临西县| 昂仁县| 响水县| 中阳县|