Dam project to be finished ahead of schedule
(Xinhua)
Updated: 2006-02-04 13:58

An executive with the China Yangtze River Three Gorges Project Development Corporation said the gigantic dam of the multi-function water control facility would be finished nine months ahead of schedule.

Cao Guangjing, deputy general manager of the corporation, said by May this year, the workers would have built the half-done dam from the southern bank of the river to the height of 185 meters.

"The Three Gorges Project will be capable of controlling the floods on the Yangtze by then and generating more electricity as the level of the water stored in the reservoir will rise from 135 meters at present to 156 meters," said Cao.

Situated near the Xiling Gorge, the easternmost gorge of the Three Gorges on the middle reaches of the Yangtze River, the Three Gorges Dam is designed to have a length of 2,309 meters and a height of 185 meters.

It will also have the functions for flood control, power generation, navigation upon completion and will be built from northern and southern banks of the flood-prone Yangtze.

Launched in 1993, the Three Gorges Project, including the 185-m-high dam and 26 generators on both banks of the Yangtze, is being built in three phases on the middle reaches of the Yangtze River, China's longest.

The preparations and construction of the first phase were carried out between 1993 and 1997. The Yangtze was dammed at the Three Gorges area for the first time on November 8, 1997.

Workers began concrete pouring for the dam from the northern bank of the Yangtze in late 1998 and completed this section of the dam, 1,600-m long, in October 2002.

Concrete pouring for the dam close to the southern bank, extending 660 m, began in July 2003 and is scheduled to finish by early 2007.

In accordance with the original plan, the Three Gorges Project, with an estimated cost of 180 billion yuan (approximately 21.7 billion U.S. dollars), will also have 26 generators with a combined generating capacity of 18.2 million kw.

So far, the workers have successfully installed 14 turbo-generators on the northern bank of the Yangtze in addition to the completion of the dam close to the northern bank.

All the 14 turbo-generators on the northern bank have been put into power generation. They generated 49.09 billion kw/hour of electricity in 2005 alone.

The entire Three Gorges Project is expected to be completed in 2009 and by then, it will be able to generate 84.7 billion kwh of electricity annually.



 
  Story Tools  
   
  Related Stories  
   
Three Gorges Dam to be open to tourists
Manufacturers, Exporters, Wholesalers - Global trade starts here.
Advertisement
         
主站蜘蛛池模板: 东乌| 浦县| 略阳县| 闽侯县| 德州市| 千阳县| 纳雍县| 睢宁县| 汉川市| 宁城县| 闻喜县| 怀集县| 柘城县| 安新县| 青阳县| 高邑县| 井冈山市| 高雄县| 寿阳县| 元朗区| 晴隆县| 弥渡县| 遂溪县| 县级市| 抚顺市| 晋宁县| 瑞安市| 九寨沟县| 溧阳市| 金乡县| 日土县| 阿勒泰市| 南阳市| 柘荣县| 喀喇沁旗| 黎川县| 珲春市| 永和县| 临湘市| 枝江市| 大安市| 永平县| 广丰县| 安塞县| 河间市| 新邵县| 阳朔县| 密云县| 博罗县| 察隅县| 绥化市| 夏邑县| 溧阳市| 察哈| 潮安县| 安远县| 彭泽县| 柞水县| 孟州市| 巴林右旗| 闽侯县| 乌兰察布市| 漠河县| 五大连池市| 大连市| 江陵县| 伊川县| 株洲县| 吉水县| 临猗县| 合江县| 宝清县| 泾阳县| 新绛县| 泽库县| 双辽市| 潜江市| 鲁甸县| 江油市| 桂林市| 南江县| 龙陵县|