Auditors: Billions squandered in Iraq

(AP)
Updated: 2007-02-16 09:50

Washington - About $10 billion has been squandered by the US government on Iraq reconstruction aid because of contractor overcharges and unsupported expenses, and federal investigators warned Thursday that significantly more taxpayer money is at risk.

The three top auditors overseeing work in Iraq told a House committee their review of $57 billion in Iraq contracts found that Defense and State department officials condoned or allowed repeated work delays, bloated expenses and payments for shoddy work or work never done.

More than one in six dollars charged by US contractors were questionable or unsupported, nearly triple the amount of waste the Government Accountability Office estimated last fall.

"There is no accountability," said David M. Walker, who heads the auditing arm of Congress. "Organizations charged with overseeing contracts are not held accountable. Contractors are not held accountable. The individuals responsible are not held accountable."

"People should be rewarded when they do a good job. But when things don't go right, there have to be consequences," he said.

Also testifying Thursday were Stuart Bowen, the special inspector general for Iraq reconstruction, and William H. Reed, director of the Defense Contract Audit Agency.

The appearance before the House Oversight and Government Reform Committee came as Congress prepares for a showdown with President Bush next month over his budget request of nearly $100 billion for the wars in Iraq and Afghanistan.

So far, the Bush administration has spent more than $350 billion on the Iraq war and reconstruction effort.

The Army, which handles most of the Iraq contracting, said Thursday it had not reviewed the latest contract figures.

"The US Army, along with the Departments of Defense and State, continue to help thousands of Iraqis daily with reconstruction projects to provide them with better lives," said spokeswoman Mary Ann Hodges. "We look forward to examining its findings and applying some of its recommendations in the future."

Senate Democrats said recently cited cases of waste were "outrageous rip-offs of the American taxpayer" and introduced legislation Thursday to stiffen punishment for war profiteers and cut down on cronyism in contracting.

According to their testimony, the investigators:

-- Found overpricing and waste in Iraq contracts amounting to $4.9 billion since the Defense Contract Audit Agency began its work in 2003. Some of that money has been recovered. An additional $5.1 billion in expenses were charged without proper documentation.

-- Pointed to growing Iraqi sectarian violence as a significant factor behind bloated US contracting bills. Iraqi officials, they said, must begin to take primary responsibility for reconstruction efforts. That is an uncertain goal, given the widespread corruption in Iraq and the local government's inability to fund projects.

-- Urged the Pentagon to reconsider its growing reliance on outside contractors in wars and reconstruction efforts. Layers of subcontractors, poor documentation and lack of strong contract management are rampant and promote waste even after the GAO first warned of problems 15 years ago.

Walker complained that GAO investigators have difficulty getting basic detail about reconstruction contracts such as expenses and subcontractors involved because many Pentagon divisions fail to consistently track or fully report them.

"It's absolutely essential if Congress wants to make an informed decision on authorizations and appropriations that we get this information," he said. "We're talking about billions of dollars and thousands of American lives at stake."

Rep. Henry Waxman, the committee chairman, has pledged scores of investigations of fraud, waste and abuse, with subpoenas if necessary, on the administration's watch.

Of the $10 billion in overpriced contracts or undocumented costs, more than $2.7 billion were charged by Halliburton Co., the oil-field services company once headed by Vice President Dick Cheney.

Noting that auditors still have $300 billion of Iraq spending to review, Waxman said the total amount of waste, fraud and abuse "could be astronomical."

"It's no wonder that taxpayers all across our country are fed up and demanding that we bring real oversight to the 'anything goes' world of Iraq reconstruction," he said.

Rep. Tom Davis, R-Va., the top Republican on the panel, pointed to ongoing, "systemic" problems in Iraq contracting. "This much is clear: Poor security, an arcane, ill-suited management structure, and frequent management changes have produced a succession of troubled acquisitions," Davis said.



Top World News  
Today's Top News  
Most Commented/Read Stories in 48 Hours
主站蜘蛛池模板: 来宾市| 遵义市| 冕宁县| 阜新市| 会同县| 东乌| 英吉沙县| 奈曼旗| 博爱县| 嘉义县| 依安县| 郓城县| 酒泉市| 洛川县| 岐山县| 剑河县| 仲巴县| 尼木县| 陇川县| 昭通市| 舟曲县| 大余县| 吴旗县| 宾川县| 桦甸市| 波密县| 正定县| 建昌县| 襄樊市| 册亨县| 桃园市| 岑溪市| 汝城县| 永年县| 榆林市| 拉孜县| 阿城市| 平山县| 临朐县| 鹿泉市| 东平县| 庆安县| 汝州市| 合阳县| 桃园县| 满城县| 怀安县| 鲁甸县| 重庆市| 广东省| 中西区| 怀来县| 长寿区| 康保县| 合作市| 灵山县| 金寨县| 株洲县| 天镇县| 桐庐县| 兴义市| 衡阳县| 湘西| 兴文县| 唐海县| 绍兴市| 阿图什市| 凤城市| 江北区| 汨罗市| 柏乡县| 农安县| 中江县| 凤冈县| 南昌县| 浦北县| 吴忠市| 油尖旺区| 吕梁市| 酒泉市| 门头沟区| 嫩江县|