Water diversion project back on fast track

2011-02-25 09:59

BEIJING?-- More than 52 billion yuan ($7.9 million) is expected to be injected into the South-to-North Water Diversion Project this year, the largest ever since the ambitious plan was kicked off eight years ago but delayed due to complicated issues.

E Jingping, top official at the office in charge of the program's construction under the State Council, announced at a conference on Thursday (Feb 24) that, in 2011, authorities will pour a record 52 billion yuan into the project, with maximum investment to exceed 60 billion yuan.

Of the fund, 33 billion yuan will be earmarked for projects in the eastern and central routes to be launched this year, with the rest to be spent on speeding up the shift of some 190,000 people slated to make way for the new water canals of the central route.

Most of them are in Central China's Hubei and Henan provinces.

To achieve the goal set for this year, E (an uncommon family name in China, most popular in Hubei province)?made it clear that local authorities should have ensured engineering progress in full sail, keep an eye on quality control, bring investment under effective control and resolve key technological problems facing the project such as swelling soil.

Also known as dilative soil or expensive soil, the problem potentially endangers up to 357 kilometers of the planned open water supply channel, or one-third of the total the central route has to go across in central China.

In the eastern route, authorities must improve water pollution control with water quality in all sections reaching grade III, the minimum standard for drinking water after being treated.

Water quality of Danjiangkou Reservoir, which will feed the main central route and areas upstream, should be up to the grade II the government set for surface water.

E urged local authorities to team up with other related authorities to deal with possible conflicts of interest as the vast water diversion project has been in "the most critical period of its construction".

The construction of the first phase of the water diversion is at risk.

Over the past eight years, only 33 individual projects out of 155 were completed, with 31 others failing to start work as scheduled, sources with E's office disclosed.

It meant that only about one-third of the phase's total investment was realized, with the remaining two-thirds having to be completed in the three years ahead.

As the world's largest water-diversion project, the project is to take water from the water-rich Yangtze River in the South to satisfy the growing demand in the parched North, including metropolises such as Beijing, Tianjin and scores of other drought-prone cities through its three routes - the eastern, central and western water diversion channels, each stretching over 1,000 km.

The first phase of the two routes has been under construction since 2002 and 2003, with the last one still on the drawing board.

Years later, their construction has been bogged down due to issues surrounding investment and complicated economic and social factors such as rising prices.

As a result, the planned completion of the first stage of the eastern and central routes was pushed back to 2013 and 2014, respectively, after it became clear that the earlier deadlines of 2010 and 2008 could not be met.

Since then, the plan has been pushed onto the fast track again, with construction in many branch sections getting into full swing. Last year, work was started on 40 delayed individual projects, with 48 billion yuan of investment involved, while the resettlement program and water pollution control, two of the decisive factors for the success of the vast water diversion project, were also pushed forward.

Last year, some 149,000 people, or 43 percent of the total slated to make way for the enlarged Danjiangkou Reservoir area, were resettled, while water quality in 83 percent of the sections the authorities have surveyed along the eastern route were reportedly up to standards, according to insiders.

Related News:

主站蜘蛛池模板: 盖州市| 伊宁县| 永安市| 高雄市| 深水埗区| 襄垣县| 吉安县| 五莲县| 宝清县| 门源| 康定县| 商河县| 巴林右旗| 贺州市| 盐边县| 登封市| 木里| 辛集市| 自治县| 黄陵县| 封丘县| 同心县| 佛冈县| 锦州市| 紫阳县| 达拉特旗| 旬邑县| 平安县| 岳阳县| 白银市| 图木舒克市| 长乐市| 茂名市| 象州县| 青田县| 平罗县| 舞阳县| 桐乡市| 博野县| 东乡族自治县| 镇赉县| 普格县| 神池县| 洛阳市| 喀喇| 云安县| 桑日县| 麦盖提县| 原阳县| 闸北区| 五河县| 崇礼县| 桑植县| 拜城县| 台江县| 丹东市| 台中市| 长葛市| 大英县| 漳州市| 太白县| 清苑县| 辽中县| 烟台市| 蒲江县| 利津县| 卓尼县| 海丰县| 湘潭县| 邹平县| 万全县| 岫岩| 镇平县| 德江县| 响水县| 金川县| 葵青区| 义马市| 开平市| 施甸县| 那坡县| 微山县|